Rome Strip Steel Renovation & Repair

Rome Strip Steel

Rome, NY

Construction Notes

The Temper Mill Foundation project consisted of a 480 yard concrete equipment foundation. There were 22 different elevations and 236 anchor bolts, which all had to be set to a 1/16" tolerance. The project was completed in 6 weeks with a 7 man crew and no remedial work was required.