This negotiated, Design-Build, Butler Building Project, is a 40,000 SF Corporate
Headquarters and Warehouse. The Owner, Mr. Frank Giotto, and his staff brought
to us preliminary plans in Mid-September of 2000. We presented our proposal for
the Building Shell and Sitework, with suggested modifications, on 9/26/00 and
received a Letter of Intent on 10/4/00.
The project proceeded immediately thereafter with site preparation, which included
removal of over 7,000 cubic yards of organic materials and replacement with structural
fill. Foundations and Butler Building erection proceeded through the harsh winter
of 2000-2001. The Warehouse was enclosed in May/June, and the Sitework completed
in July allowing the owner to occupy in early August. Having proceeded with the
project through the winter months allowed the owner to occupy (4) months earlier
then waiting until the following spring would have alllowed.
The striking exterior of the (2) story 20,000 SF Office Building utilizes exterior
insulation finish system, aluminum and glass, and ground face masonry units which
shows the versatility of the Butler Building System.
* Further information about this and other Butler Design-Build projects can be obtained by
contacting David L. Kleps, Vice President of the Design-Build Butler Building Department.
|
|